Warning Referenced Activities
Type: Selection
Range: The settings listed below
Default: Common_warning_default
When an activity is referenced in one of the sequencing attributes of a sequential resource or in one of the level modification attributes of a parallel resource, but is not referenced in the attribute “activities” of that resource, AIMMS will issue a warning. Consider the following example:
SET:
identifier : mySet
indices : i, j, k
definition : data { a, b, c, d, e, f, g, h, i, j, k } ;
RESOURCE:
identifier : res
usage : sequential
schedule domain : Timeline
activities : act(i):ord(i)<5
comes before : (act(‘f’),act(‘g’)) ;
AIMMS will issue the warning message: The activity act(‘f’) referenced in the attribute “comes before” of resource res, is not scheduled on that resource.
The option “Warning_Referenced_Activities
” determines how activities referenced in a sequencing or level modification attribute, but not in the activities attribute, are reported, depending on the following settings:
|
Do not issue a warning. |
|
Issue a warning and post it to the global error and warning collector. |
|
Take action depending on the option ‘Common warning default’. |
|
Issue a warning and post it to the nearest error handler. |
|
Take action depending on the option ‘Strict warning default’. |
|
Issue an error. |
|
In a developer system same as Error, in a deployment system same as Warning_handle |
|
In a developer system same as Error, in a deployment system same as Off |
|
In a developer system same as Warning_handle, in a deployment system same as Off |
Note
With the option Maximal Number of Warnings Reported you can set the maximal number of warnings that are shown in errors/warnings and message window.